(031) 3990555
Fax (031) 3990666
Combustion Chamber
- 4 August 2022
- Posted by: user
- Category:
No Comments
Combustion ChamberBlade Ring
- 4 August 2022
- Posted by: user
- Category:
Blade RingTBBM Tegal Baru
- 15 March 2021
- Posted by: user
- Category:

PLTU JERANJANG, NTB (2×25 MW)
- 26 January 2017
- Posted by: user
- Category:
Kapasitas : 2x25 MW Scope : EPC Klien : PT. PLN (Persero) Tahun : 2012 KembaliPABRIK BIOETHANOL
- 26 January 2017
- Posted by: user
- Category:
Kapasitas : 100 KI/Day Scope : EPCI & Commissioning Klien : PTPN X Tahun : 2012 KembaliPABRIK SAGU
- 26 January 2017
- Posted by: user
- Category:
Kapasitas : 100 Ton/Day Scope : EPCI & Commissioning Klien : PT Perhutani Tahun : 2016 KembaliPENSTOCK PARMONANGAN
- 26 January 2017
- Posted by: user
- Category:
Kapasitas : 2x4,5 MW Scope : Waterway Installation Pipe, Penstock Pipe, Powerhouse Building Structure and Hydromechanical Klien : PT. Hutama Karya (Persero) EPC Division Tahun : 2016 KembaliCoal Fired Steam Power Plant NTB 2X25 MW
- 26 January 2017
- Posted by: user
- Category:
Coal Fired Steam Power Plant NTB, Jeranjang 2x25 MW Capacity : 2x25 MW Client : PT. PLN (Persero) Scope : EPC & Commisioning Year : 2014Walesi Micro Hydro Power Plant
- 26 January 2017
- Posted by: user
- Category:
Walesi Micro Hydro Power Plant Capacity : 500kW Client : PT.PLN (Persero) Scope : EPCI & Commissioning Year : 2012Belawan Gas Power Plant
- 26 January 2017
- Posted by: user
- Category:
Belawan Gas Power Plant Capacity : 1x 48 MW Client : PT.PLN (Persero) Scope : EPCI & Commisioning Year : 2008